Concrete Footing Calculator
Estimate concrete and rebar for continuous strip footings under walls and square pad footings under posts and piers. Get cubic yards, bag counts and ready-mix cost in one step.
Concrete Footing Calculator: Strip & Pad Footing Volume Guide
Footings are the widened concrete base that spreads the weight of a house, garage, addition, deck or wall over enough soil to stop it settling. There are two common types in residential work: continuous (strip) footings that run under foundation walls and block walls, and isolated pad (spread) footings that sit under individual posts, piers or columns. This calculator handles both in one estimate so you can price a whole foundation in a single step.
Strip footing volume is simply length × width × depth. A typical residential footing under an 8" foundation wall is 16"–20" wide and 8"–10" deep. Under the 2021 IRC (Table R403.1(1)), the minimum footing thickness is 6" and required width depends on the number of stories, the wall type and the allowable soil bearing pressure — a one-story house on 1,500 psf soil can use a narrower footing than a two-story brick-veneer house on the same soil. Every 1" of extra depth on a 120 ft run adds roughly 0.6 cubic yards of concrete for a 16"-wide footing.
Pad footings are usually square: 16" × 16" × 8" for small deck posts, 24" × 24" × 12" for heavier beam posts and porch columns, and 30"–36" square or larger for posts carrying roof or second-floor loads. The bottom of every footing must sit on undisturbed soil below the local frost depth, which ranges from about 12" in the South to 48" or more in northern states.
For 2026 budgeting, ready-mix concrete averages about $150–$185 per cubic yard in most US metros, with short-load fees of roughly $50–$150 when you order under 4–5 yards. #4 rebar costs about $11–$15 per 20 ft stick. Installed by a contractor, residential strip footings typically run $10–$20 per linear foot including excavation, forms, rebar and concrete, while precast or poured pad footings for decks run about $75–$200 each depending on size and access.
Most footing problems come from ordering too little concrete because trench sides were not straight. Earth-formed footings (poured directly against trench walls) almost always use more concrete than the drawings show, so many contractors add 10–15% on top of the calculated volume. Forming the footing with 2× lumber gives a cleaner, more predictable pour but adds labor. Either way, keep rebar up off the dirt on chairs or bricks so it ends up with about 3" of concrete cover.
Continuous (Strip) Footing
Pad (Spread) Footings
How to Use This Calculator
Understanding Your Result
The highlighted ready-mix figure is rounded up to the nearest quarter yard, which is how most suppliers sell concrete. If it is under about 4–5 yards, expect a short-load fee. The rebar line gives both installed footage and the number of 20 ft sticks to buy.
Key Formulas
Strip Footing Volume
Use the total length of all footing runs. Divide by 27 for cubic yards.
Pad Footing Volume
1,728 cubic inches = 1 cubic foot.
Strip Rebar
The 1.10 adds roughly 10% for lap splices and corner bends.
Worked Example
A 30 × 30 ft garage with a 120 ft perimeter strip footing, 16" wide × 8" deep, with two continuous #4 bars.
- 1Width = 16 ÷ 12 = 1.333 ft; Depth = 8 ÷ 12 = 0.667 ft
- 2Volume = 120 × 1.333 × 0.667 = 106.7 cu ft
- 3Add 10% waste = 117.3 cu ft = 4.35 cu yd → order 4.5 cu yd
- 4Rebar = 120 ft × 2 bars × 1.10 = 264 ft
- 520 ft sticks = 264 ÷ 20 = 13.2 → 14 sticks (about 176 lb of #4 bar)
Order 4.5 cu yd of ready-mix (about $675–$835 at $150–$185/yd plus any short-load fee) and 14 × 20 ft #4 bars (about $155–$210).
Assumptions Behind This Estimate
- 10% waste allowance on concrete; earth-formed trenches may need 15%
- Ready-mix sold in ¼ cubic yard increments
- #4 rebar weight 0.668 lb/ft; strip rebar includes 10% for laps
- Pad footing rebar is a #4 grid at 12" on center with 3" cover on each side
- Does not include stepped footings, thickened slab edges or piers above the pads
Concrete per 10 ft of Strip Footing
| Footing Size (W × D) | Cu Ft per 10 ft | Cu Yd per 10 ft | Cu Yd per 100 ft |
|---|---|---|---|
| 12" × 6" | 5.0 | 0.19 | 1.85 |
| 16" × 8" | 8.9 | 0.33 | 3.29 |
| 20" × 8" | 11.1 | 0.41 | 4.12 |
| 20" × 10" | 13.9 | 0.51 | 5.14 |
| 24" × 12" | 20.0 | 0.74 | 7.41 |
Earth-formed trenches typically need 10–15% more than these figures.
Before You Buy: Practical Advice
- Call 811 before digging so buried utilities are marked — it is free and required in every US state.
- Dig to undisturbed soil. If you over-dig, fill the extra depth with concrete, not loose dirt.
- Book the footing inspection before the concrete truck; most inspectors need to see trench depth and rebar placement.
- Set the top of footing forms level with a laser or transit so the wall or block above starts level.
- Install vertical dowels or keyways now if a poured wall or block wall will sit on the footing.
Frequently Asked Questions
How do I calculate concrete for a footing?
Multiply length × width × depth in feet to get cubic feet, then divide by 27 for cubic yards. A 120 ft strip footing that is 16" wide and 8" deep is 120 × 1.333 × 0.667 = 106.7 cu ft, or 3.95 cu yd. Add 10% for waste and uneven trenches, giving about 4.35 cu yd — order 4.5 yards.
How deep and wide should a footing be?
Under the IRC, footings must be at least 6" thick and 12" wide, and they must bear below the local frost line. Common residential sizes are 16"–20" wide × 8"–10" deep for foundation walls and 24" × 24" × 12" for post pads. Required width increases with more stories, heavier wall materials and weaker soil, so confirm with your plans or building department.
Does a footing need rebar?
The IRC does not require rebar in every plain concrete footing, but many jurisdictions, engineers and seismic design categories do. A typical detail is two continuous #4 bars in strip footings with 3" of cover, and a #4 grid in larger pad footings. Rebar also helps the footing bridge soft spots in the soil.
How much does a concrete footing cost?
Materials alone for a 120 ft × 16" × 8" strip footing are about $675–$835 for 4.5 yards of ready-mix plus around $160–$210 for 14 sticks of #4 rebar in 2026. Contractor-installed strip footings usually run $10–$20 per linear foot including excavation and forms. Individual deck post footings typically cost $75–$200 each installed.
Should I use bags or ready-mix for footings?
Use bags for a handful of small pad footings (under about 1 cubic yard total). For continuous footings, ready-mix is almost always the better choice: 4 yards would take 180 bags of 80 lb mix, and mixing that by hand risks cold joints and inconsistent strength.
Related Calculators
Concrete Wall Calculator
Estimate the poured wall that sits on the footing.
Open CalculatorRebar Calculator
Price rebar for slabs and footings.
Open CalculatorSonotube Calculator
Concrete for round piers above pad footings.
Open CalculatorConcrete Block Fill Calculator
Grout for block walls built on footings.
Open CalculatorHelpful Guides
Dive deeper with these related guides to plan your project with confidence.